(605) 367-1036 info@jsaengineers.biz

Project Information
Project Bid Price: $2,827,211.98
Completion Date: October 31, 2017
Project is currently to be completed in the Spring of 2018

JSA Engineers and Land Surveyors is a private engineering and surveying firm hired by the City of Canton to perform the construction administration services for the project. Please contact any of the following project team members if you have any questions or concerns.

JSA Engineers/Land Surveyors
Myron Adam, PE/LS
Project Manager
myron@jsaengineers.biz
Office: 605.367.1036
Cell: 605.359.2796

JSA Engineers/Land Surveyors
Devin Clay, EI
On-site Representative
devin@jsaengineers.biz
Office: 605.367.1036
Cell: 605.690.0035

City of Canton
Bill Thorson
Director of Public Works
bill.thorson@cantonsd.org
Office: 605.987.2881

Hulstein Excavating, Inc.
Construction Contractor
Jeff Haas, Project Manager
jeff@hulexinc.com
Office: 507.442.2006
Cell: 507.215.5934

To sign up and receive bulletins by email send an email to myron@jsaengineers.biz or call 605.359.2796.

Over the past two weeks, progress on following items was achieved:
– Finished installing sanitary sewer main on Dakota Street.
– Sawcut pavement for removals on Kimball Street.

No significant items of work were completed by the private utility companies this period.

The following work is anticipated over the next couple of weeks.
· Finish installing sanitary sewer services along Dakota St.
· Install storm sewer main through the intersection of Maple St. Construct new storm sewer inlets/boxes.
· Begin installing water main from Maple St to Lynn Ave.
· Pour concrete driveways between 4th St and 2nd St.
· Begin paving Dakota St. from 2nd St to Maple St.

Current Street Closures
– Dakota St from 4th to Lynn – CLOSED.
– Intersections open at 4th St and 3rd St
** 4th Street and 3rd Street intersections currently open to through

The contractor expects to be completed with the project by October 31, 2017. This is only an estimate and may vary due to weather or other unforeseen circumstances.

If you have a disability or limitation which may require special accommodations for access, please contact the JSA office. This project bulletin will be distributed by email every two weeks during construction, and will be posted on the City’s website.
If you wish to discontinue receiving these project updates, please contact Myron Adam at myron@jsaengineers.biz so you can be removed from the email distribution list.